Road Construction Contract Review
Updated: Nov 3
Start Date: 3/4/26
Why the Office of the City Auditor (OCA) did this project
The City Auditor sought citizen input to identify areas of greatest public concern. Road construction emerged as a top priority and aligned with active risk topics being tracked by the Internal Audit team. The City fiscal year bond issuance for roads was $116,530,000. Without adequate monitoring procedures in place, this level of spending creates the opportunity for meaningful waste or financial abuse that could go undetected. That said, the City has managed to limit change orders to 3% or less over the last 9 years.
Project Scope
This limited review focuses on those risks considered most relevant to the City and the related constituent questions. A sample of ten road contracts was selected based on identified risk attributes to assess whether existing processes were sufficient to monitor those risks, and to determine whether any unmitigated risks resulted in adverse consequences to the City.

Why audit this topic?
Contracts were identified as a risk in the Fiscal Year 2026 Annual Audit planning process based on input from city councilors, department head interviews, and surveys of residents, employees, and auditors.
Project Procedures
This project was co-sourced with SOAR Partners, a Tulsa-based third-party provider of internal audit and other consulting services.
Review projects with higher significant change orders
Review the implementation of incentives or penalties that existed within the existing
contracts
Review compliance with using small business entities (City expectation being 10%)
Review how inspectors are selected
Review whether a current certificate of insurance was retained in the documentation
Review whether any vendors were used very frequently (potentially showing favoritism)
Key Observations
There were no findings related to non-compliance with City requirements.
Improvement Opportunities:
Add final inspection and project completion approvals to final documentation
checklist and verify inclusion of certificates of insurance
Improve documentation of liquidated damages assessments and waivers
Consider establishing a delegated approval authority that allows Engineering or Public Works to authorize change orders that fall below a defined dollar threshold
Audit Objective
Review selection of road construction contracts to assess whether existing processes are sufficient to monitor risks, and to determine whether any unmitigated risks have resulted in adverse consequences to the City.
Observations
Within our sample of 10 contracts, we did not have any reportable observations related to non-compliance with City requirements. However, as we assessed the possible risks, we did identify some improvement opportunities that might strengthen/mature the City’s risk mitigation strategy related to Road Construction projects.
Improvement Opportunities
Final Documentation Package
OBSERVATION |
We noted two documentation issues. One related to certificates of insurance where 4 of 10 documentation packets reviewed were missing certificates of insurance, and 1 included an initial certificate but lacked the updated certificate required for the remainder of the project. We also noted that the final inspection approvals and project completion documentation were not included in the final documentation package. |
RECOMMENDATION |
The certificates of insurance are already included in the checklist for final documentation, so we only suggest increased diligence on its inclusion. We suggest adding final approvals, indicating that all inspections have been performed and work is deemed adequately completed, to the checklist. |
MANAGEMENT RESPONSE |
CERTIFICATES OF INSURANCE: We agree that maintaining strong diligence around the inclusion of certificates of insurance is important. We did verify in the PW Field Engineering project files for all contracts noted that final payments were made within the policy coverage periods. However, contract no. 135981 the payment of retainage was paid after the expiration of the COI. We will continue to require the completion of partial and final payment checklists to support compliance with this requirement. FINAL APPROVALS ON INSPECTIONS NOTED: Pay application packets, both partial and final, must contain the approval signatures of the Construction Manager and the Field Engineering Manager. Their approvals are certifying the items and their respective quantities have been installed and being paid for in accordance with the construction documents. PW will ensure that this information is in both the PW Field Engineering project files and in the payment documents stored in our Enterprise Resource Planning system. |
Liquidated Damages Assessment and Waiver
OBSERVATION |
A review of project files identified a few compliance gaps with potential liquidated damages implications. One project lacked a critical path method (CPM) schedule—an omission that reduces the City's ability to evaluate the legitimacy of contractor-requested time extensions and to substantiate any resulting liquidated damages assessment. Additionally, 4 projects exceeded their contracted completion dates, but we could not tell if liquidated damages had been waived or assessed. We also noted that one project failed to meet its small business entity (SBE) participation requirements. We again could not ascertain whether the liquidated damages related to that had been waived (on a form 5) or not. |
RECOMMENDATION |
When liquidated damages are triggered and could be assessed by the City, there should be clearer documentation that states whether it was assessed or waived. When a waiver is granted, the City should document the basis for the waiver along with any required approvals within the final billing package. Where a penalty has been assessed, it should appear as a distinct line item in the billing records to ensure transparency and accountability. |
MANAGEMENT RESPONSE |
When liquidated damages (vs Penalties) are assessed, PW will ensure that this information is clearly documented in both the PW Field Engineering project files and in the payment, documents stored in our Enterprise Resource Planning system. |
Change Orders have Zero Tolerance
OBSERVATION |
Current City policy requires Council approval for all change orders, regardless of dollar value. Because the Council convenes only periodically, this process routinely introduces approval delays of two to three weeks—delays that can stall active construction, disrupt contractor schedules, and prolong impacts on neighboring businesses and residents. We understand that the Council has approved all submitted change orders, suggesting that the current zero-dollar threshold may impose a procedural burden without a commensurate benefit of pre-approval. |
RECOMMENDATION |
We suggest the City consider establishing a delegated approval authority that allows the Engineering or Public Works department to authorize change orders that fall below a defined dollar threshold such as a fixed ceiling amount and/or a specified percentage of the original contract (Purchase Order) value. This tiered approach would preserve Council's oversight while reducing unnecessary delays on smaller, routine scope adjustments. |
MANAGEMENT RESPONSE |
Management concurs that this would add eiciency and benefits to constituents and vendors. This approach is being used by the Oklahoma Department of Transportation and the Oklahoma Turnpike Authority. |